Database of Waste Management Technologies Life

Cost of Waste Treatment Technologies

In the following, the user may find a list of data regarding the cost of the various treatment options. Data refer to investment and operational cost and are gathered via literature review, information from plants in operation as well as from the questionnaires distributed during the implementation of Action 1 of the project.

MBT (general)

Commercial Name (if available) Location Capacity, tpa Technology Investment Cost, m€ Investment Cost, €/tpa Operational Cost, €/ton Gate Fee, €/ ton
    25.000 ΜΒΤ 12.2 488 24 - 81  
    60.000 MBT 13.5 225 24 - 81  
    100.000 MBT 56 560
120.000 MBT 42 350 55
200.000 MBT 40.5 203 24 - 81

Anaerobic Digestion (alone or in MBT)

Commercial Name (if available) Location Capacity, tpa Technology Investment Cost, m€ Investment Cost, €/tpa Operational Cost, €/ton Gate Fee, €/ ton
10.000 – 20.000 Anaerobic Digestion 300 - 400 74 – 88
20.000 AD of source separated organics 22 – 27 44 - 55
Passavant Roediger Anlagenbau GmbH3 20.000 AD 12.4 620
25.000 Anaerobic Digestion 235 - 245
Valorgen3 25.000 AD 15.4 616
BEKON26 25.000 Complete dry AD 8-9 320-360
Passavant Roediger Anlagenbau GmbH3 40.000 AD 19.0 475
Ashford 40.000 Anaerobic Digestion 11.8 295 44 - 52
Vaasa 40.000 Anaerobic Digestion 6.2 155 39.1 39.1
<50.000 Anaerobic Digestion 219 – 575 31.5
50.000 Anaerobic Digestion 11 – 29.5 220 - 590 26 - 60
50.000 ΜΒΤ with Anaerobic Digestion 21 420 110 - 160
>50.000 Anaerobic Digestion 147 – 381 22 - 95
50.000 – 60.000 Anaerobic Digestion 13.5 – 35 270 – 583 38 54 – 94.5
Arrow Bio1 Tel Aviv, Israel 70.000 Wet AD 11.5 165 21-25,51
6-252
Amiens 72.000 Anaerobic Digestion 1.2 16 49 37.7
Oaktech 75.000 AD 17.6 235
75.000 Anaerobic Digestion 135 - 180
100.000 MBT with Anaerobic Digestion 35 350 95 - 140
100.000 Anaerobic Digestion 12 - 35
100.000 Anaerobic Digestion 7.5 - 18 75 - 180 21
Hese Leicestershire, UK 110.000 Hydrolysis and AD 45 395
120.000 Wet AD without post composting 20 – 30 167 – 250
120.000 Wet AD with post composting 25 – 36,5 208 – 304
120.000 MBT with Anaerobic Digestion 40 333 88 - 135
Linde Madrit, Spain 140.000 Wet AD + tunnel composting 35 250
150.000 MBT with Anaerobic Digestion 57 380 80 - 120
ISKA 150.000 Percolation + AD + composting 40 267 70 (without disposal compost costs and RDF)
200.000 MBT with Anaerobic Digestion 8 15 – 51.5 75 – 258 18
Global Renewables 200.000 Percolation + AD + composting 52.5-57.5 263 – 288 50-90
Valorgen 200.000 AD 51.5 258
SBI Heerenveen, Netherlands 220.000 AD 38 173 89.3
Ecopark 2, Barcelona 240.000 (of which 120.000 tons SSO) MBT with aerobic composting + AD of source selected organics 68.4 285 The Environment Agency of Barcelona is the owner of all facilities and pays 100 €/ton: 15€ to cover investment and 85€ to cover operation
Ecopark 1, Barcelona 245.000 MBT with aerobic composting + AD of source selected organics (SSO) 130.2 (includes refurbishment of digesters) 531
Ecopark 3, Barcelona 260.000 MBT with wet AD 58.8 226
Farington Waste Recovery Park – Lancashire (UK) 305.000 MBT-AD, Composting & MRF 140.3 460
Vargon 328.000 MBT with Anaerobic Digestion 19.1 58 39.1 39.1

MRF

Commercial Name (if available) Location Capacity, tpa Technology Investment Cost, m€ Investment Cost, €/tpa Operational Cost, €/ton Gate Fee, €/ ton
Karditsa, Region of Thessalia, Greece 12.000-15.000 MRF with trommel, magnet and handpicking 2.37 NA
Alexandroupoli, Eastern Macedonia & Thrace, Greece 12.000-15.000 MRF with magnet ballistic separator and handpicking 2.35 NA
Elefsina, Attika, Greece 30.000 MRF with trommel, magnet, eddy current, ballistic separator, handpicking and NIR 5.39 NA
50.000 General data by HERCCO for an MRF of 50.000 tpa 5.0 100 40

Composting (alone or in MBT)

Commercial Name (if available) Location Capacity, tpa Technology Investment Cost, m€ Investment Cost, €/tpa Operational Cost, €/ton Gate Fee, €/ ton
Alpheco 1.000 Batch tunnel system 75.000 75
10.000 – 20.000 Windrows 25.7
10.000 – 20.000 In vessel 8.1 40.5 - 81 47 – 54
Ipswich 17.200 In vessel composting of source separated organics 1.85 108 25
Entsorga, Turtle Q-Ring Kefallonia Island, Greece 20.000 MBT with composting in boxes with semi-permeable sheet 3.0 150 33
Horstmann 20.000 Tunnel with RDF production 2.1 105
20.000 In vessel composting of source separated organics 300 - 900 40 - 80
20.000 In vessel composting of source separated organics 0.7 – 1.2 35 - 60
Entsorga, Coccinelle composting system21 25.000 Composting in boxes 7.2 29 25
SRS Inverboyndle, UK 25.000 In vessel composting 3.75 150 52.5-59
35.000 MBT with RDF production and composting 9.5 – 15.0 271 – 429 55 - 70
40.000 Windrow composting 1.5 – 12 38 – 240 14 – 61
40.000 In vessel composting 12 – 16 300 – 400 23 – 61
Vinci Environment4 Launay – Lantic – France 40.000 MBT with open windrow composting 3.65 91 30
Horstmann Osterholz 45.000 MBT with RDF production & tunnel composting 12 267 60
<50.000 Composting 96 – 205 192
Bedminster 50.000 In vessel composting 19.1 382
50.000 MBT with composting 15 300 61 - 95
Linde Linz, Austria 50.000 Tunnel composting 19 380
Alpheco3 50.000 Batch tunnel system 5 100
50.000 Simple composting system 3.5 – 22 70 – 440 30 - 60
>50.000 Composting 38 – 308 27 - 95
60.000 In vessel composting of source separated organics 200 30 - 35
Sistema 60.000 MBT with RDF production 11.8 167
70.000 MBT with RDF production and composting 14 – 21 200 – 300 47 - 52
Chania, Crete, Greece 70.000 (nominal) Actual: 25.000 tpa MSW 13.158 tpa co-mingled dry recyclables from source separation MBT with mechanical separation, handpicking and closed composting system 30.0 2.550.000€/y
~67 €/ton of actual input
45 (includes landfill)
VKW 75.000 In vessel composting 15.5 207 34
Biodegma1 Neumünster, Germany 50.000 MSW +35.000 bulky Closed composting (covered windrows) 59
Linde1 Borken, Germany 85.000 Tunnel composting 14.5 171
Civic1 90.000 Vertical composting reactor 19.5-22.5 217 – 250 52,5-103,51
51,5-1322
100.000 Windrow composting 33
100.000 In vessel composting of source separated organics 50 - 250 20 - 55
100.000 MBT with composting 27 270 54 - 80
100.000 In vessel composting 52
100.000 Simple composting8 7.5 – 29.5 75 – 295 33
100.000 MBT with RDF production and composting 17.5 – 27.5 175 – 275 40 - 50
120.000 In vessel composting of source separated organics 180 28 - 30
120.000 MBT with RDF production and composting in open windrows 18.5 – 32.5 154 – 271 23 – 39
120.000 MBT with RDF production and in vessel composting 20 – 39.0 167 – 325 26 - 47
Schwanebeck 150.000 In vessel composting 73 487 74 118
VKW1 150.000 In vessel composting 27 180 25.5
150.000 MBT with composting 31 207 48 – 73
Larnaka, Cyprus 176.000 MBT with handpicking, NIR and in vessel composting 60 341 NA
Sistema 180.000 MBT with RDF production 36.8 204
200.000 In vessel composting 47 235
200.000 Simple composting system 25 – 59 125 – 295 28
GRL 200.000 51.6 – 66.5 258 – 308 59 - 89
Biodegma Pößneck, Germany 200.000 Closed composting (covered windrows) 22,5-331
6824
200.000 MBT with composting 40 200 45 - 70
Bedminster 200.000 In vessel composting 52.4 262
100.000 – 200.000 MBT with RDF production and composting 68 - 96
200.000 – 400.000 48 - 68
Bedminster Edmonton, Canada 193.750 MSW + 53.540 sewage sludge Bio-cylinder (aerobic treatment) 55.9 226 45.91
45.62
Bedminster 250.000 In vessel composting 65.8 263 46
Ecopark 4, Barcelona 260.000-300.000 + 40.000 SSO MBT with advanced recycling and closed composting 45 150
Kelag Istanbul 300.000 MBT with metal recovery, handpicking, RDF production and hall composting 47 157 6.30
Facility of Mechanical Recycling and Composting Waste
Ano Liosia, Attika
400.000 (nominal) MBT with RDF production, metal recovery, bio-cylinder and composting in closed hall 64.4 161
Horstmann 500.000 Tunnel with RDF production 20.6 42
Sutco In vessel composting 109,5-129 (with and without residue disposal, relatively)

MBT Biodrying

Commercial Name (if available) Location Capacity, tpa Technology Investment Cost, m€ Investment Cost, €/tpa Operational Cost, €/ton Gate Fee, €/ ton
Nehlsen Rugen, Germany 20.000 MBT Biodrying 5.2 (without RTO & SRF pelletization ) 260
Nehlsen Lubben, Germany 28.000 MBT Biodrying 4.8-7.5 171 – 268
Entsorga, Hebiot biodrying system 60.000 MBT Biodrying 14 233 15
Nehlsen Stralsund, Germany 70.000 MBT Biodrying 9.8-17.5 140 – 250
ECODECO Heraklion, Crete 75.000 MBT Biodrying without SRF refinement stage 14 187 21.31
ECODECO 75.000 MBT Biodrying (typical values for 75.000 tpa module, with post-treatment section) 20 267 19.8
100.000 Biodrying 8 – 25 80 – 250 73 - 103
Entsorga, Hebiot biodrying system 120.000 MBT Biodrying 24 20 - 60 25

Incineration

Commercial Name (if available) Location Capacity, tpa Technology Investment Cost, m€ Investment Cost, €/tpa Operational Cost, €/ton Gate Fee, €/ ton
33.000 Incineration of SRF 34 – 39 1030 – 1181 191 - 205
50.000 Incineration 450 - 610
50.000 Incineration 20 – 30 400 – 600
50.000 Incineration 32 640
60.000 Incineration 50 833
60.000 Incineration of SRF 47 – 53 783 – 883 136 - 145
ECODECO S.r.l – A2A Group Corteolona, Italy 63.929 tons/y SRF
597 tons/y Filter-pressed Biological Sludge
Bubbling Fluidised Bed 35.0 542 124 75 (€) /t SRF for 2009
90 (€) /t sludge for 2009
50.000 – 100.000 Incineration 37.5 375 - 750 98
50.000 – 100.000 Incineration 40 - 75
50.000 – 100.000 Incineration 30 – 82 600 – 820
Kotka Kotkafinland 100.000 56 560
100.000 Incineration 41 410 7.9
100.000 Incineration 60 600
100.000 Incineration 54 – 62 540 – 620 55.4 – 86.5
100.000 – 200.000 Incineration9 61.5 – 86.5 433 - 615 12.6 - 27
100.000 – 200.000 Incineration 77 - 404 770 – 2020
100.000 - 200.000 Incineration 89 – 116
100.000 Incineration 390 - 530 60 - 80 65 - 80
120.000 Incineration 64 - 73 533 – 608 87 - 96
150.000 Incineration 80
150.000 Incineration 55 - 80
200.000 Incineration 105 525
200.000 Incineration 69.5 343 12.64
200.000 Incineration 78.4 – 86.5 392 – 433 40.5 - 61
SYSAV Malmo – Sweden 200.000 Moving grate 107 (2001) 535 46 80
200.000 Incineration 320 - 450 50 55 - 60
250.000 Incineration 290 55
300.000 Incineration 149 497
300.000 Incineration 102.5 342 15.8
300.000 Incineration 330 - 390
400.000 Incineration 130.5 326 18.17
400.000 Incineration 115 – 162 288 - 405
400.000 Incineration 250 - 430 55
500.000 Incineration 156.5 313 22.12
500.000 Incineration 245
600.000 Incineration 189.5 316 24.49
600.000 Incineration 390 650 55
300.000 – 600.000 Incineration 52 - 68
700.000 Incineration 217.5 311 27.65
Incineration 73.5 – 117.6

PFI projects in Great Britain

Also some data are included in the following table, regarding PFI projects in Great Britain:

Authority Plants/Capacity in tpa Budget (Μ€)
Kirklees WtE: 136.000
MRF: 27.000
Composting: 5.000
37,97
South Gloucestershire In Vessel Composting (IVC): 30.000
4 transfer stations
38,42
Surrey 2 WtE: 270.000
In Vessel Composting (IVC): 112.000
MRF: 40.000
95,76
Central Berkshire MRF & transfer station: 430.000 41,44
ELWA 2 ΜΒΤs: 360.000
7 MRFs
700 collection points
1 road
52,64
Leicester City ΜΒΤ: 175.000
Anaerobic Digestion: 35.000
34,54
West Berkshire MRF: 13.500
IVC: 32.000
31,91
Cornwall WtE: 240.000 50,40
Nottinghamshire WtE: 180.000
MRF: 85.000
42,91
Lancashire 2 ΜΒΤs: 350.000
2 IVC units: 110.000
1 MRF: 50.000
100,80
Northumberland WtE (extension): 136.000
1 transfer station: 70.000
3 MRFs: 70.000
11 MRF extensions: 54.000
2 transfer stations (extensions): 75.000
45,70
Shropshire Waste Partnership IVC: 60.000
WtE: 90.000
45,70
Wakefield Metropolitan District Council MBT: 175.000
1 MRF: 50.000
IVC: 40.000
36,96
Greater Manchester Waste Disposal Authority 5 MBTs: 550.000
1 MRF: 90.000
4 IVC units: 175.000
WtE (CHP): 325.000
139,44
London Borough of Southwark MBT: 87.500
2 ΚΔΑΥ: 95.700
ΣΜΑ: 20.000
38,64
Cambridgeshire County Council MBT: 240.000
IVC: 90.000
39,20
Cheshire County Council MBT: 300.000
RDF incineration: 150.000
44,80
Merseyside Waste Disposal Authority 2 MBTs for RDF production: 655.000
2 RDF incinerations: 327.000
100,80
North Yorkshire County Council & City of York Council MBT: 145.000
WtE: 180.000
MRF: 40.000
72,80
Leeds WtE (CHP): 160.000 76,83
Suffolk WtE (CHP): 245.000
IVC: 77.000
MRF: 60.000
114,24
Bradford MBT: 251.000
IVC: 44.000
WtE (CHP): 113.000
69,55
Barnsley, Doncaster and Rotherham WtE (CHP): 152.177
MBT for RDF production: 80.371
86,69
South Tyne & Wear WtE (CHP): 200.000 or
IVC for CLO production: 200.000
82,32
Staffordshire WtE (CHP): 300.000 137,09
Leicestershire WtE (CHP): 180.000 96,99
South West Devon Waste Partnership WtE (CHP): 225.000 106,40
Gloucestershire WtE (CHP): 175.000 103,04
Hertfordshire WtE (CHP): 270.000 129,14
Norfolk WtE (CHP): 155.000 101,92
South London Waste Partnership 2 MBTs: 213.000
WtE (CHP): 106.500
126,45